CONNECTION PROCEDURE - B3, B4 AND OTHER BIG CONSUMERS

DOCUMENTS REQUIRED

  1. Application & Agreement Form(With Load Details)
  2. Abridged Conditions of Supply
  3. Attested Copy of I.D. Card of Applicant
  4. Attested Copy of I.D. Card of Witness
  5. Property Proof
  6. Specified Affidavit (It shall be provided along with A&A Form)
  7. Memorandum and Articles of Association
  8. Form-29 (List of Directors)
  9. Form-A (List of Share Holders)
  10. Resolution from Board of Directors in favour of signatory
  11. NOC from Owner in Case of Tenant

TIME SCHEDULE FOR ISSUANCE OF DEMAND NOTICE AND ENERGIZATION OF CPP / SPP/SELF / PRIME GEN CONSUMERS

Activity/Details
Days
A.D(P&E) for survey, preparation of proposal and estimation
7 days
D.D(P&E) for discussion, checking and joint note
3 days
Sr. Manager(P&E) for evaluation of different proposals
3 days
C.Engr/Tech Director for approval
2 days
Chief Executive for approval
1 day
Preparation of Technical Clearance & Demand Notices
2 days
Time Up to Issuance of Demand Notices
18 days
After payment of DN and Test Report
Verification of Test Report by concerned XEN
5 days
Issuance of SCO and Release Order
3 days
Energization by committee
10 days
Total Connection Time(where no construction work is involved)
36 days
Total Connection Time (where construction work is involved)
36+ days

(Time taken by applicant for payment of DN excluded)