CONNECTION PROCEDURE - Domestic (A1),
Commercial (A2), Industrial (B1, B2) & OTHERS
Documents required
- Application Form
- Abridged Conditions of Supply
- Attested Copy of National Identity Card of Applicant
- Attested CopY of National Identity Card of witness
- Attested Copy of Property Ownership Proof
- NOC from Owner in case of Tenant
Additional Documents For Industrial Connections (FOR Limited Companies)
- Resolution from Board of Directors in Favor of Signatory
- Certified True Copy of Memorandum of Articles of Association
- Certified True Copy of Form-29
Estimated TIME SCHEDULE (FOR B1 and B2 Connections)
| Sr.
# |
Activity/Details |
Days |
| PHASE
1 |
1 |
Registration |
1 |
2 |
Survey & Estimation |
2 |
3 |
Demand Notice (DN) of Capital/Security |
7 |
| PHASE TIME |
10 |
| PHASE
2 - After payment of DN and Test Report (where required) |
1 |
Wiring Test Report Verification |
5 |
2 |
Service Connection Order(SCO)/Material Release Order(RO) |
2 |
3 |
Energization of Connection |
10 |
| PHASE TIME |
17 |
| TOTAL CONNECTION TIME |
27 |
(Time taken by applicant for payment of DN excluded)
Procedural mechanism
- The DN can be collected by the applicant on specific date given on
the receipt of application from concerned office, otherwise it will
be dispatched through post.
- Payment of DN is to be made in the designated bank/branch.
- Test Report is to be submitted alongwith the payment of security in
the bank.
- Test report shall be verified by concerned office.
- Release Order will be issued by Sanctioning Authority along with SCO.
|
|