| Activity/Details |
Days |
| A.D(P&E) for survey, preparation of
proposal and estimation |
7 days |
| D.D(P&E) for discussion, checking and
joint note |
3 days |
| Sr. Manager(P&E) for evaluation of
different proposals |
3 days |
| C.Engr/Tech Director for approval |
2 days |
| Chief Executive for approval |
1 day |
| Preparation of Technical Clearance &
Demand Notices |
2 days |
| Time Up to Issuance of Demand Notices |
18 days |
| After payment of
DN and Test Report |
| Verification of Test Report by concerned
XEN |
5 days |
| Issuance of SCO and Release Order |
3 days |
| Energization by committee |
10 days |
| Total Connection Time(where no construction
work is involved) |
36 days |
| Total Connection Time (where construction
work is involved) |
36+
days |