BUDGET & EXPENDITURE STATEMENT

BUDGET & EXPENDITURE STATEMENT IN RESPECT OF SENIOR MANAGER (CONST) CIRCLE LESCO LIMITED FOR THE MONTH of 12/2011 (Actual)

Sr. No.
Particulars
Budget
Expenditure
Material
Installation
Charges
C/Work
Consultant Fee
Total
Material
Installation
Charges
Contractor Fee
Consultant Fee
Total
1
System Augmentation Programs (For Distribution of Power and Rehabilitation)
  H.T New Line & Extension of Existing Lines
290.625
58.125
19.875
6.375
375
25.414
28.375
1.975
0.248
56.012
  L.T New Line & Extension of Existing Lines
135.625
27.125
9.275
2.975
175
79.297
35.866
2.67
0.675
118.508
  Village Electrification
0
  Total
426.25
85.25
29.15
9.35
550
104.711
64.241
4.645
0.923
174.52
2
Deposit Work
 
Village Electrification
-
-
-
-
-
47.36
15.22
11.935
1.976
76.49
 
Other Deposit works
-
-
-
-
-
89.964
70.879
18.417
3.314
182.574
 
Total
0
0
0
0
0
137.324
86.099
30.352
5.29
259.065
 
Grand Total
426.25
85.25
29.15
9.35
550
242.035
150.34
34.997
6.213
433.585